BlueCielo Meridian REFSYS 2012 Configuration Guide | BlueCielo ECM Solutions |
The settings that control the revision numbers of documents in the Plant group are described in the following table.
Setting |
Default |
Description |
---|---|---|
REVISION_INITIAL |
Initial revision (not used). |
|
REVISION_LEVEL1_FIRST |
0 |
Scheme for the first level revision (master document). |
REVISION_LEVEL2_FIRST |
A |
Scheme for the second level revision (project copy). |
REVISION_LEVEL3_FIRST |
R1 |
Scheme for the third level revision (sub-project). |
REVISION_NUMLEN |
2 |
The length of the plant revision number. |
REVISION_INCREMENTONPROJECTCOPY |
false |
True increments the revision number when a document is added to a project. False increments it when the document is released from a project. |
REVISION_SEPARATOR |
. |
Characters used to separate the revision number elements. |
Major revision numbering is used when a document is released as a master document revision. Minor revision numbering is used for revisions within a project.
The result of configuring the revision number as shown in the preceding table is:
Related concepts