Locking a master document

Locking a master document prevents it from being revised either directly by document workflow or indirectly by a project copy other than the one that is locking it. A locked master document may only be revised by the project copy from which the lock was placed.

A master document can be locked by either of two methods:

Note    

To lock a master document to an existing project copy:

  1. Select the project copy for which you want to lock its master document.
  2. From the Document menu, point to Master/Project Copy, and click Lock Master Document.

A red lock icon will appear next to the master document in the Navigation view to indicate that it has been locked in a project folder. Its Locked property will also be set to Locked in project. The master document may then not be revised until the project lock has been removed.

The lock may be removed by either releasing the project copy as a new revision of the master document or by manually unlocking it as described in Unlocking a master document.