Configuring interlock objects and scope
The objects and scope to which an interlock applies determine what is affected by the interlock, either the project itself or any number of sub-projects.
To configure an interlock’s objects and scope:
- Select the desired project definition in the configuration tree in the left pane of Meridian Enterprise Configurator.
- Click the Edit button to enable modification of the project definition.
- Click the Interlocks tab in the right pane. The list of interlocks applied to the current project definition appears in the right pane.
- Select the interlock you want to edit and click the Edit button. The Properties dialog of the interlock appears.
- Click the Objects and Scope tab. The selected object and scope options applied to the interlock appear as shown in the following figure.
- Enable the options on this tab from the descriptions in the following table.
Option | Description |
---|---|
Project itself |
This interlock will only apply to the current project. |
Subprojects of this Project |
This interlock will only apply to sub-projects of the current project. |
All subprojects |
This interlock will apply to all sub-projects of the current project. |
Any subproject |
This interlock will apply to any sub-projects of the current project. |
No subprojects |
This interlock will apply if there are no sub-projects of the current project. |
- Click OK to close the Properties dialog.
- Click the OK button on the Objects and Scope tab to save your changes.
This completes the configuration of the interlock objects and scope of a project definition. You can now continue to configure the project definition in any of the following topics.