You are here: Unlinking from a master document

Unlinking from a master document

Unlinking from a master document can be useful if the project copy was originally made from a master document but the project copy should no longer be released as a revision of the master document but instead released as a new master document. Unlinking the project copy will remove from the master document the reference that was created when the project copy was made from the master document. Unlinking will also unlock the master document if it was locked when the project copy was made.

To unlink a project copy from a master document:

  1. Select the project copy that you want to unlink.
  2. From the Document menu, point to Master/Project Copy, and click Unlink from Master Document. A confirmation dialog may appear.
  3. Click Yes. The project copy is unlinked from the master document.

Related tasks

Copying a project copy to another project folder

Discarding a document from a project

Showing master and project copies

Linking to a master document