Reconciling with an updated master document
When the master document of a project copy has changed since the project copy was made, the master document may contain more or less information than the project copy, possibly making the project copy obsolete. You can reconcile the difference between the two documents by one of three commands:
- Discard from Project: This assumes that because of whatever changes were made to the master document, the project copy is now obsolete and the project copy should be destroyed.
- Confirm Superseded by Master: This assumes that because of whatever changes were made to the master document, the project copy is now obsolete. In this situation, the system retains the project copy and its reference to the master document for future reference, but makes the project copy inactive. The system also prevents the project copy from being released as a new master document revision.
- Confirm Merged with Master: This assumes that the changes made to the master document have also been made to the project copy. This option should be used after you have physically merged changes in the master document with the project copy. In this situation, the system retains the project copy and its reference to the master document for future reference. The system will allow the project copy to be released as a new master document revision (possibly after additional changes are made to the project copy) after which the project copy becomes inactive.
To reconcile a project copy of a changed master document:
- In PowerUser, select the project copy to be reconciled.
- From the Document menu, select Master/Project Copy. Based on the descriptions above, click either Discard from Project, Confirm Superseded by Master, or Confirm Merged with Master.